PHMSA Advisory Bulletin (ADB–2012–10) Pipeline Safety: Using Meaningful Metrics in Conducting Integrity Management Program Evaluations
[Docket No. PHMSA–2012–0279]
The
Department of Transportation/Pipeline Hazardous Materials Safety Administration
(PHMSA) issued Advisory Bulletin ADB-2012-10 to remind operators of gas
transmission and hazardous liquid pipeline facilities of their
responsibilities, under Federal integrity management regulations, to perform
evaluations of their integrity management programs using meaningful performance
metrics. ADB-2012-10 outlines 11 key elements for these evaluations.
A critical program element of an operator’s integrity management program is the
systematic, rigorous evaluation of the program’s effectiveness using clear and
meaningful metrics. When executed diligently, this self-evaluation process will
lead to more robust and effective integrity management programs and improve
overall safety performance. This process is critical to achieving a mature
integrity management program and a culture of continuous improvement. Program
evaluation is a required integrity management program element as established in
§§192.911(i) and 195.452(k) for gas transmission and hazardous liquid
pipelines, respectively.
In light of NTSB’s findings following the San Bruno gas transmission incident,
PHMSA is reminding operators about the importance of these requirements.
Operators are advised to critically review their processes and methods for
evaluating integrity management program performance and take action to
strengthen these processes where warranted.
In addition, operators must keep records supporting the decisions, analyses,
and processes developed and used in their evaluation of integrity management
program effectiveness. These records should include those justifying the
selection of performance metrics, the performance metric data and trends, and
how these metrics are used to improve the integrity management program.
For a copy of the Advisory Bulletin ADB-2012-10, contact Jessica Roger.
MAOP Exceedance Reporting
The
Department of Transportation/Pipeline Hazardous Materials Safety Administration
(PHMSA) has requested that States share the information below to those
operators with gas transmission assets in the pipeline industry. Please review
your internal reporting procedures and modify to capture the information
outlined below.
The passage below was included in Section 23 of the federal “Pipeline
Safety, Regulatory Certainty, and Job Creation Act of 2011” passed by
Congress and effective January 3, 2011.
“(2) EXCEEDANCES OF MAXIMUM ALLOWABLE OPERATING PRESSURE.—If there is an
exceedance of the maximum allowable operating pressure with respect to a gas
transmission pipeline of an owner or operator of a pipeline facility that
exceeds the build-up allowed for operation of pressure-limiting or control
devices, the owner or operator shall report the exceedance to the Secretary and
appropriate State authorities on or before the 5th day following the date on
which the exceedance occurs.”
PHMSA is reportedly working on an electronic filing system for submission of
these reports, and is also reportedly working on an Advisory Bulletin to
explain its expectations. For a time, PHMSA suggested that operators hold
information on an overpressure event until that system was operational.
However, these actions have been delayed. PHMSA is now requesting that
overpressure events be reported to InformationResourcesManager@dot.gov
using the same format as a Safety Related Condition Report (SCRC).
The format for a Safety Related Condition Report is found in the federal
regulations at 49 CFR §191.25(b). With a few modifications to make that format
appropriate for MAOP exceedance reporting, the report should contain the
following content: The report should be titled “Gas Transmission MAOP
Exceedance” and provide the following information:
- Name and principal address of operator.
- Date of report.
- Name, job title, and business telephone number of person submitting the report.
- Name, job title, and business telephone number of person who determined that the condition exists.
- Date condition was discovered and date condition was first determined to exist.
- Location of condition, with reference to the State (and town, city, or county) or offshore site, and as appropriate, nearest street address, offshore platform, survey station number, milepost, landmark, or name of pipeline.
- Description of the condition, including circumstances leading to its discovery, and any significant effects of the condition on safety.
- The corrective action taken before the report is submitted and the planned follow-up future corrective action, including the anticipated schedule for starting and concluding such action.
This list does not specifically ask for the cause of the
overpressure, but that should certainly also be included in the report, if
known. Also include basic pipeline information such as pipeline size, length,
normal operating pressure, and MAOP. It is presumed the “build-up
allowed” will be based on 49 CFR 192.201.
NOTE:
These reports are required for gas
transmission pipelines only.
The law states that such reports must be filed within five (5) days. You are
reminded that if a report like this is made to PHMSA, an intrastate operator
must concurrently file a copy with the appropriate State Agency.
PHMSA Technical Advisory Committee Meetings December 11-13, Washington, DC
On
November 27, 2012, in the Federal Register, the Pipeline and Hazardous
Materials Safety Administration (PHMSA) announced meetings of the Liquid
Pipeline Advisory Committee and the Gas Liquid Advisory Committee, also known
as the Technical Hazardous Liquid Pipeline Safety Standards Committee and the
Technical Pipeline Safety Standards Committee.
The meetings will be held at the Westin Alexandria, 400 Courthouse Square,
Alexandria, VA 22314, Phone: 703-253-8600. Meetings scheduled as follows:
- Tuesday (Dec 11): 1:00 pm to 4:00 pm – Liquid Pipeline Advisory Committee Meeting.
- Wednesday (Dec 12): 9:00 am to 5:00 pm – Joint Committee Meeting (Liquid and Gas)
- Thursday (Dec 13): 9:00 am to 1:00 pm- Gas Pipeline Advisory Committee Meeting
The committees will meet to discuss two proposed rules, the first
to implement changes to the administrative procedures in Part 190 Enforcement
Procedures, and the second to establish criteria and procedures for determining
the adequacy of state pipeline excavation damage prevention law enforcement
programs; to establish an administrative process for making adequacy
determinations and Federal requirements PHMSA will enforce in states with
inadequate programs; and to establish the adjudication process for
administrative enforcement proceedings against excavators where Federal
authority is exercised.
For more information, contact Cheryl Whetsel, Advisory Committee Manager by
phone at 202-366-4431 or by email.
The meetings will not be Web cast; however, presentations will be available on
the meeting website and posted in the E-Gov website: http://www.regulations.gov under docket number
PHMSA-2009-0203 within 30 days following the meeting.
Click here for more detailed information and a
PDF copy of the notice.
API/AOPL Pipeline Performance Tracking System (PPTS) Workshop January 29, 2013 – Houston, TX
The API/AOPL Data Mining Team (DMT) will host the bi-annual Pipeline Performance Tracking System (PPTS) workshop on January 29, 2013 in Houston, TX. The workshop will be hosted at the RCP offices in Houston, TX and also via Live-Meeting. The PPTS workshop is open to all current and prospective PPTS participants. Covered topics include: what is reportable to PPTS, how to report to PPTS, benefit of reporting to PPTS, how does PPTS relate to PHMSA report data, and how the data is used for industry purposes. Registration information will be sent out as the event approaches. For further information, please contact Bukky Adefemi at adefemia@api.org.
These articles are maintained and updated as new information becomes available.
Regulatory Watch: Key Dates & Deadlines
Track PHMSA rulemaking, regulatory stages, and important compliance deadlines in RCP's Regulatory Watch.
View Full Regulatory Watch →Conference News
Pipeline Pigging and Integrity Management Conference
The 39th International Pipeline Pigging & Integrity Management Conference (PPIM) will take place at the George R. Brown Convention Center in Houston. The event brings together pipeline operators, engineers, and industry professionals to explore advancements in pipeline inspection, integrity management, risk assessment, and emerging technologies.…
RCP Team Attending
Heather Roark
Jessica FoleyPSI Training Schedule

| Date | Training Course | Price | Registration |
|---|---|---|---|
| Nov 17 – Nov 19, 2026 | DOT Pipeline Compliance Workshop | $2,150 | SOLD OUT |
| Feb 16 – Feb 18, 2027 | Pipeline Safety Audit Training | $2,150 | Register → |
| Feb 23 – Feb 25, 2027 | Advanced Pipeline Risk Assessment Workshop | $2,150 | Register → |
| Mar 23 – Mar 25, 2027 | DOT Pipeline Compliance Workshop | $2,150 | Register → |
WEBINAR RECORDING!
Unpacking the Key Updates in API RP 1170 & 1171, 2nd Edition
Unpacking the Key Updates in API RP 1170 & 1171, 2nd Edition
RCP and the Pipeline Safety Institute offered a free webinar exploring the 2nd Editions of API RP 1170, Design and Operation of Solution-mined Salt Caverns Used for Natural Gas Storage and API RP 1171, Functional Integrity of Natural Gas Storage in Depleted Hydrocarbon Reservoirs and Aquifer Reservoirs. Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!
New Workshop Alert!
Prepare Your Team for Pipeline Safety Audits with Confidence!
Our 3-day Pipeline Safety Audit Workshop is tailored for professionals responsible for the safe operation of hazardous liquid and natural gas pipelines. Designed for groups of 10-15 participants, this interactive training…
On-Site Training Request
We have conducted on-site training for oil and gas companies for over 25 years and can provide customized workshops for companies with groups of five or more.
Season’s Greetings from RCP!
RCP would like to thank our valued clients for a wonderful year. We appreciate the opportunities you have given us to serve as your Professional Engineers, Regulatory Experts, and Trusted Partners. We look forward to working with you on even more projects in the years ahead. Best wishes for the holiday season and the New Year, from your friends at RCP.
Sincerely,
![]()
W. R. (Bill) Byrd, PE
President
RCP Inc.
- PHMSA Advisory Bulletin (ADB–2012–10) Pipeline Safety: Using Meaningful Metrics in Conducting Integrity Management Program Evaluations
- MAOP Exceedance Reporting
- PHMSA Technical Advisory Committee Meetings December 11-13, Washington, DC
- API/AOPL Pipeline Performance Tracking System (PPTS) Workshop January 29, 2013 – Houston, TX
- Ongoing Resources
- Regulatory Watch: Key Dates & Deadlines
- Conference News
- PSI Training Schedule