Joint Industry Comments Submitted to Docket

Joint industry comments from API, INGAA, AGA and APGA have been submitted to the docket for the pending notice of proposed rulemaking “Safety of Gas Transmission Pipelines: Repair Criteria, Integrity Management Improvements, Cathodic Protection, Management of Change, and Other Related Amendments”. This NPRM is one of three rules that were split out of the original NPRM, commonly known as the Gas Mega-Rule. To read the these comments as well as other comments, go here. The final Gas Piping Advisory Committee meeting is scheduled to discuss the NPRM “Safety of Gas Gathering Pipelines” on September 6th and 7th in Arlington, Virginia.

GAO Report on PHMSA / State Inspection Resource Needs

GAO-18-461: Published: May 29, 2018. Publicly Released: May 29, 2018

The Government Accountability Office (GAO) has recently looked into federal and state responsibilities for interstate pipeline inspections. While PHMSA expanded its inspector workforce by 25% between 2012 and 2017, the agency hasn’t planned for future workforce needs—for example, it hasn’t assessed how states can help with pipeline inspections and safety oversight. GAO has recommended that PHMSA should develop a workforce plan for interstate pipeline inspections that is consistent with leading practices in workforce planning, which should include a consideration of the additional resources and safety oversight that state pipeline officials can provide. DOT concurred with GAO’s recommendation and provided technical comments, which were incorporated as appropriate. The complete report can be found on the GAO’s website.

Gas Pipeline Advisory Committee (GPAC)

The next GPAC meeting is scheduled for Thursday, September 6, 2018 from 8:30 a.m. to 5:00 p.m. and on Friday, September 7 from 8:30 a.m. to 1:00 p.m. The GPAC meeting will discuss the NPRM, Pipeline Safety: Safety of Gas Gathering Lines. (See related article in the April 2018 edition of the DOT Pipeline Compliance News: GPAC Summary – Safety of Gas Transmission and Gathering NPRM.) The meeting location, agenda and any additional information will be published on the PHMSA Meeting Registration webpage.

Audit of FERC Certification Process

The Office of Inspector General within the Department of Energy has published a report from its recent audit of the Federal Energy Regulatory Commission’s Natural Gas Certification Process (a.k.a. a FERC Certificate). Excerpts from that report include:

  • While nothing came to our attention to indicate that natural gas certification applications had been inappropriately approved or disapproved, FERC can take steps to improve aspects of the natural gas certification process
  • . . . we identified four areas for improvement that, if addressed, could aid FERC in more efficiently and effectively managing its natural gas certification process:
    • Process Transparency
    • Public Access to FERC Records
    • Tracking Stakeholder Comments
    • Data Integrity
  • The process transparency and public access issues that we identified above occurred, in part, because FERC had not specifically designed its public-facing systems for use by the general public.
  • Management concurred with the report’s recommendations and indicated that it had either initiated or planned corrective actions to address the issues identified in the report.

The full report can be found here.

Changes to Excavation Damage Prevention Rules in Mississippi

The State of Mississippi has recently revised Title 77 – Public Utilities and Carriers; Chapter 13 – Regulation of Excavations Near Underground Utility Facilities. In addition to various changes to the existing rules on excavation damage prevention, the rule creates a new Design Information Request, requiring response within 7 days by utility owners to a person providing professional services and making a request in preparation for bidding, preconstruction engineering, or other advance planning efforts that do not involve excavation. There is also a new section that includes the creation of a new Underground Facilities Damage Prevention Board charged with enforcement and the creation of an Underground Damage Prevention Fund which will be used by the Board.

Ongoing Resources

These articles are maintained and updated as new information becomes available.

Regulatory Watch: Key Dates & Deadlines

REGULATORY SNAPSHOT Last updated November 3, 2026
38Tracked regulations
8Proposed / DFR
18Final rules

Track PHMSA rulemaking, regulatory stages, and important compliance deadlines in RCP's Regulatory Watch.

View Full Regulatory Watch →
Last Updated: October 2026

Conference News

Jan252027

Pipeline Pigging and Integrity Management Conference

▦ January 25, 2027 – January 28, 2027⌖ George R. Brown Convention Center, Houston, TX

The 39th International Pipeline Pigging & Integrity Management Conference (PPIM) will take place at the George R. Brown Convention Center in Houston. The event brings together pipeline operators, engineers, and industry professionals to explore advancements in pipeline inspection, integrity management, risk assessment, and emerging technologies.…

Exhibiting · Booth 524
RCP Team Attending
Heather RoarkHeather Roark
Jessica FoleyJessica Foley
Event Details

Last Updated: November 2026

PSI Training Schedule

Date Training Course Price Registration
Nov 17 – Nov 19, 2026 DOT Pipeline Compliance Workshop $2,150 SOLD OUT
Feb 16 – Feb 18, 2027 Pipeline Safety Audit Training $2,150 Register →
Feb 23 – Feb 25, 2027 Advanced Pipeline Risk Assessment Workshop $2,150 Register →
Mar 23 – Mar 25, 2027 DOT Pipeline Compliance Workshop $2,150 Register →

WEBINAR RECORDING!
Unpacking the Key Updates in API RP 1170 & 1171, 2nd Edition

RCP and the Pipeline Safety Institute offered a free webinar exploring the 2nd Editions of API RP 1170, Design and Operation of Solution-mined Salt Caverns Used for Natural Gas Storage and API RP 1171, Functional Integrity of Natural Gas Storage in Depleted Hydrocarbon Reservoirs and Aquifer Reservoirs. Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!

WEBINAR RECORDING
Pipeline Safety: Unpacking the Class Location Change Requirements

Thank you to everyone who attended and participated in this informative webinar. The session recording is posted to our YouTube channel. Please watch, like, and subscribe to our channel!

New Workshop Alert!

Prepare Your Team for Pipeline Safety Audits with Confidence!

Our 3-day Pipeline Safety Audit Workshop is tailored for professionals responsible for the safe operation of hazardous liquid and natural gas pipelines. Designed for groups of 10-15 participants, this interactive training…

On-Site Training Request

We have conducted on-site training for oil and gas companies for over 25 years and can provide customized workshops for companies with groups of five or more.

We would welcome the opportunity to discuss our services with you.

Sincerely,

W. R. (Bill) Byrd, PE
President
RCP Inc.