In This Issue

PHMSA Updates Hazardous Liquid Integrity Management FAQ’s

On February 8, 2011, PHMSA published several updates to the pipeline integrity FAQ’s for hazardous liquid pipelines. The revised FAQ’s are listed below.

7.4 What is an ‘immediate repair condition’?

An immediate repair condition is a detected anomaly involving:

  • Metal loss greater than 80% of nominal wall regardless of dimensions.
  • Predicted burst pressure less than the maximum operating pressure at the location of the anomaly. (Where burst pressure has been calculated from the remaining strength of the pipe using a suitable metal loss strength calculation, e.g., ASME/ANSI B31G).
  • Dents on the top of the pipeline (above 4 and 8 o’clock position) with any indicated metal loss, cracking, or a stress riser.
  • Dents on top of the pipeline with a depth greater than 6 percent of nominal pipe diameter.
  • Significant anomaly that in the judgment of the person evaluating the assessment results requires immediate action.

Repairs must be made as soon as practicable. An operator must reduce pressure (to a level calculated using the formula in section 451.6.2.2 (b) of ASME/ANSI B31.4 as applicable (see FAQ 7.15)) as soon as safety allows and operate at or below that pressure until a repair can be made.

7.15 The rule requires that an operator temporarily reduce pressure if an immediate repair condition is discovered (195.452(h)(4)(i)). With respect to this requirement:

a. Can the temporary reduction in operating pressure be based upon previous maximum operating pressures?


No. A reduction in operating pressure is intended to provide an additional safety margin until the defect can be remediated. To assure that additional margin is provided, the pressure reduction must be based upon pressures that the pipe has actually experienced, with the defect present (i.e., pressures for which safety has been demonstrated). These may be well below the “maximum operating pressure” for the pipe.

The rule requires that the pressure reduction must be calculated using the method in section 451.6.2.2 (b) of ANSI/ASME B31.4 if that method is applicable and the information needed is available. If that method cannot be used, the operator is responsible for determining an appropriate basis for assuring additional safety through a reduction in pressure. A reduction of 20 percent below the highest operating pressure actually experienced at the location of the defect within the two months preceding the inspection may provide the necessary additional safety margin.

b. Can the temporary reduction in operating pressure be based on calculations other than those defined in section 451.6.2.2 (b) of ASME/ANSI B31.4?

The method described in section 451.6.2.2 (b) of ASME/ANSI B31.4 is required by the rule and must be used for all circumstances for which it is appropriate (e.g., corrosion). There are anomalies defined by the rule as immediate repair conditions for which the method of section 451.6.2.2 (b) is not applicable (e.g., dents). These are addressed in c. below. PHMSA Pipeline Safety is considering a change to the rule to recognize that section 451.6.2.2 (b) is not applicable to all immediate repair conditions, and may also allow alternative methods for calculating the required reduction in pressure. Until the rule is changed, however, the specified method must be used in all instances in which it applies.

c. Is section 451.6.2.2 (b) of ASME/ANSI B31.4 applicable for calculating the temporary pressure reduction required for top-side dents with metal loss (195.452(h)(4)(i)(C)) and dents greater than 6% of the pipe diameter (195.452(h)(4)(i)(D))?

No. The calculation in Section 451.6.2.2 (b) of ASME/ANSI B31.4 is applicable to determining the remaining strength of pipe with corrosion defects or grind repairs (i.e., loss of wall thickness). Pressure must be reduced for other types of immediate repair conditions, but operators must develop appropriate engineering justification for the amount of pressure reduction. A reduction in operating pressure is intended to provide an additional safety margin until the defect can be remediated. To assure that additional margin is provided, the pressure reduction must be based upon pressures that the pipe has actually experienced, with the defect present (i.e., pressures for which safety has been demonstrated). These may be well below the “maximum operating pressure” for the pipe.

A reduction of 20 percent below the highest operating pressure actually experienced at the location of the defect within the two months preceding the inspection may provide the necessary additional safety margin.

7.20 Is a 20 percent reduction in pressure an adequate interim measure for immediate repair conditions?

A reduction of 20 percent below the highest operating pressure actually experienced at the location of the defect within the period immediately preceding the inspection (e.g., two months) may provide the necessary additional safety margin. Operators should evaluate each situation to determine if additional reduction, or line shutdown, is needed. Operators must use Section 451.6.2.2 (b) of ASME/ANSI B31.4 to calculate the required pressure reduction for all situations in which it applies (as required by 452(h)(4)(i)). See FAQs 7.15 and 7.22 for more information.

7.22 Section 195.452(h)(4)(i) requires that I temporarily reduce pressure in response to an immediate repair condition. The same paragraph also requires that I must calculate the reduction using the formula in section 451.6.2.2 (b) of ASME/ANSI B31.4. If using that formula results in a calculated safe pressure that is higher than my original operating pressure, must I still reduce pressure? To what?

Yes. A pressure reduction is required to provide additional safety margin until an immediate repair condition can be addressed. PHMSA Pipeline Safety expects that situations in which the calculated safe pressure using the formula in section 451.6.2.2 (b) of ASME/ANSI B31.4 is higher than the original operating pressure will be rare. Nevertheless, if the calculated pressure is greater than the existing operating pressure, pressure must still be reduced to provide the necessary margin. Operators should determine the amount of such reduction based on their particular circumstances.

Operators should also note that the specified formula only applies to metal loss anomalies (i.e., corrosion). It does not apply to immediate repair conditions that do not involve metal loss, nor does it apply to dents with metal loss. For those circumstances, operators must determine an acceptable method for calculating an acceptable reduced operating pressure. A reduction of 20 percent below the highest operating pressure actually experienced at the location of the defect within the two months preceding the inspection may provide the necessary additional safety margin.