In This Issue

PHMSA Updates DIMP FAQ’s

The following Distribution Integrity Management Frequently Asked Questions were updated or added on March 10, 2011.

C.3.8 What do operators need to have implemented by August 2, 2011?

By August 2, 2011, operators of gas distribution systems (other than a master meter or small LPG operator) must have developed and implemented an integrity management program that includes a written integrity management plan. The plan must include the operator’s procedures used to develop the seven elements listed in § 192.1007(a)-(g) At a minimum, an operator must have taken the following actions:

  1. Developed and demonstrated an understanding of their system;
  2. Identified and considered threats to each gas distribution facility
  3. Completed a risk evaluation and ranking of their distribution system;
  4. Developed criteria for deciding when risks require measures to reduce them;
  5. Determined the measures to reduce risk;
  6. Begun implementing the measures to reduce risk or have a plan to implement measures to reduce risk which includes an implementation schedule;
  7. Assessed the effectiveness of their leak management program and taken steps, if necessary, to correct deficiencies;
  8. Established a baseline measurement for each performance measure required by 192.1007(e)(1)(i)-(v);
  9. Developed performance measures to evaluate the effectiveness of measures to reduce risk, have a plan to collect the performance measure data, and begun collecting data to establish a baseline measurement;
  10. Determined the appropriate period for conducting DIMP program evaluations;
  11. Reported performance measures required by 192.1007(g) for calendar year 2010;
  12. Collected data as needed for mechanical fitting failures resulting in hazardous leaks beginning January 1, 2011; and
  13. Identified records requiring retention and have maintained them.


C.4.a.5 What comprises “reasonably available” information?

PHMSA does not intend that operators expend excessive effort, review every record available in their archives, or explore every nuance about their pipelines. At the same time, PHMSA expects that operators will devote sufficient effort to develop as thorough an understanding of their pipelines as they can while using reasonable effort.

The availability of records will vary among operators. Some operators may retain records for many years and others only for the length of time required by Part 192. Some data is stored electronically and some is paper based. Additionally, some records are stored on-site and other records may be stored off-site, such as at regional offices or long term storage facilities. Any record which the operator can access is reasonably available. All records required by Parts 191 and 192 are reasonably available. Operators need to review all records that are relevant to the current condition of the pipe or have a significant impact on the integrity of the pipe. For example, a steel pipe may have been brought under adequate cathodic protection five years ago but was not under cathodic protection in prior years. Any records showing that the pipe was not under cathodic protection, is relevant to the current condition of the pipe.

Operators must identify additional information that is needed to fill gaps due to missing, inaccurate, or incomplete records and develop a plan to collect it. They may collect this information through their normal activities including those that go beyond those activities specified in Part 192. For example, missing facility location, material and condition data can be gained when the pipe is located and/or exposed.

Operators could involve maintenance personnel in their information collection activities, surveying them about unusual circumstances they have encountered in their activities and/or asking them to review resulting system descriptions and identify any information they believe is useful that is not already included.

C.4.a.6 Must an operator’s plan include the sources used to demonstrate an understanding of its gas distribution system?

An operator needs to be able to demonstrate to regulators that they have an understanding of their gas distribution system developed using sources of information that are “reasonably available”. The plan should identify the information sources. Examples of sources that are reasonably available include documents, records, field notes, maps, historical procedures and design standards, bill of materials, procurement records and specifications, and information obtained from subject matter experts. These sources are used to identify the characteristics of the pipeline’s design, operations and environmental factors that are necessary to assess the applicable threats and risks to the distribution system. Operators also need to consider information gained from past design, operations, and maintenance. In order to verify that an operator has met this requirement, the inspector may ask the operator for information about the sources such as: the name of the documents, the time period covered by the documents, the document’s location and format (e.g. electronic, paper, or subject matter expert interview, etc.), the forms used to collect data, the fields on the forms, the instructions used to complete the forms, and a history of how this information collection changed over time.

C.4.b.3 The DIMP requirements include knowing the condition of facilities that are at risk for potential damage from external sources. Cross bores of gas lines in sewers have been reported at 2-3 per mile in high risk areas – predominately where trenchless installation methods were used for gas line installs and where sewers and gas lines are in the proximity of each other. Does the potential for cross bore of sewers resulting in gas lines intersecting with sewers need to be determined?

Yes, the threat of excavation damage includes consideration of potential or existing cross bore of sewers which have resulted in gas lines intersecting with sewers. Pursuant to § 192.1007(a)(2), the operator must consider information gained from past design, operations, and maintenance. If operators used trenchless technologies without taking measures to locate sewer laterals and other unmarked facilities during construction, there may be a risk that their facilities were installed through the foreign facility. If this excavation damage threat applies to the operator, they must evaluate its risk to their system. Depending on the results of the risk evaluation, they may need to identify and implement measures to reduce this risk to existing and future facilities.

C.5.4 Since there is a new form for mechanical fitting failures which result in a hazardous leak, do these failures still need to be reported under Part C of the Annual Report?

Yes, operators need to include all mechanical fitting failures which result in hazardous leaks eliminated or repaired as part of the total leaks reported on the Annual Report in Part C – TOTAL LEAKS AND HAZARDOUS LEAKS ELIMINATED/REPAIRED DURING YEAR. Additionally, they must report detailed information about each mechanical fitting failure which results in a hazardous leak on a separate Gas Distribution Mechanical Fitting Failure Form (PHMSA F–7100.1–2).

PHMSA created the new Mechanical Fitting Failure Report form [PHMSA F 7100.1-2] to address the new annual reporting requirement established by DIMP for hazardous leaks on mechanical fittings. Operators may submit data at anytime and at any frequency throughout the year (preferred), or they may submit all mechanical fitting failure reports in one submission. Regardless of the method they select, the reports must be submitted by March 15, 2012 for failures which occurred in calendar year 2011. If an operator does not experience any mechanical fitting failure which results in hazardous leaks, they do not need to submit a Mechanical Fitting Failure Report form. The online system for the new Mechanical Fitting Failure Report form [PHMSA F 7100.1-2] is now in operation.

NOTE: Online submission via PHMSA Portal is required unless an alternative reporting method is granted by PHMSA. More information is available at PHMSA’s, Office of Pipeline Safety web site, Pipeline Safety Community, located at http://www.phmsa.dot.gov/pipeline and click the “Online Data Entry” hyperlink listed in the first column.

C.8.3 What do master meter and small LPG operators need to have implemented by August 2, 2011?

By August 2, 2011, master meter operators and small LPG operators must have developed and implemented a written integrity management program that includes a written integrity management plan. The plan must include the operator’s procedures used to develop the elements listed in §192.1015(b)-(c). At a minimum, these operators must have taken the following actions:

  1. Developed and demonstrated an understanding of their system;
  2. Identified and considered threats to each gas distribution facility;
  3. Completed a relative risk ranking of each identified threat to the distribution system;
  4. Developed criteria for deciding when risks require measures to reduce them;
  5. Determined the measures to reduce risk;
  6. Begun implementing the measures to reduce risk or have a plan to implement measures to reduce risk which includes an implementation schedule;
  7. Are monitoring the number of leaks eliminated or repaired on its pipeline and their causes.
  8. Determined the appropriate period for conducting DIMP program evaluations; and
  9. Identified records requiring retention and have maintained them.